Name of City and/or County:
St. Joseph
Name of Plan or Project:
Cook Road Corridor
Report Period:
7/1/2016 to 6/1/2017
Name of the Person Who Prepared this Annual Report:
Rich Karleskint - Budget Financial Analyst
City or County Contact Agency:
Private Sector Developer:
Greystone Partners Land Development LLC
Original Date Plan/Project Approved:
Most Recent Plan Amendment:
03/01/2009
The project area is located at the northeast corner of Cook Road and Woodbine Road.
Description of Plan/Project:
1 Private project improvements that will consist of the development of a residential subdivision on approximately 185 acres of land into over 350 single family and townhouse housing units, 2 improvements to Cook Road resulting in a three-lane section, concrete curb and gutter, storm water drainage, and raised grass medians, 3 sewer system improvements including a new pump station 4 the construction of a 2,000 ft. waterline
Plan/Project Status:
Under Construction
How was the "but-for" Determination Made?:
Number of Relocated Residences During This Report Period:
0
Number of Relocated Businesses During This Report Period:
0
Number of Parcels Acquired Through Use of Eminent Domain Power During This Report Period:
0
Identify Any Businesses That Have Relocation to the Redevelopment Area During this Report Period:
Estimate of Retained Jobs:
0
TIF REVENUE DEPOSITS TO THE SPECIAL ALLOCATION FUND AS OF THE REPORT DATE:
Payments in Lieu of Taxes (PILOTs):
Total Received since inception:
$1,031,172.88
Amount on Hand: (As of Report Date)
$0.00
Economic Activity Taxes (EATs):
Total Received since inception:
$4,491.81
Amount on Hand: (As of Report Date)
$0.00
Total Revenue on hand in the Special Allocation Fund as of Report Date:
EXPENDITURES FOR TOTAL PROJECT COSTS FUNDED BY TIF:
Total Since Inception:
Report Period Only:
Public Infrastructure (streets, utilities, etc):
Site Development (grading, dirt moving, etc):
Rehab of Existing Buildings:
Acquisition of Land or Buildings:
AMOUNT PAID ON DEBT SERVICES:
Payments of principal and interest on outstanding bonded debt:
This Reporting Period:
$0.00
Reimbursement of developer for eligible cost:
Since Inception:
$2,461,633.01
This Reporting Period:
$0.00
Reimbursement to city/county (or other public entity) for eligible costs:
This Reporting Period:
$0.00
ANTICIPATED TIF REIMBURSEMENT COSTS:
Public Infrasture and Site Development Costs:
$492,786.00
Property Acquisition and Relocation Costs:
$0.00
Project Implementation Costs:
$20,000.00
Total Anticipated TIF Reimbursable Project Costs:
$5,539,786.00
ANTICIPATED TOTAL PROJECT COSTS:
$19,375,786.00
MATURITY OF TIF OBLIGATIONS:
Original Estimate (# of Years to Retirement):
23
Current Anticipated Estimate (# of Year to Retirement):
23
ESTIMATED INCREASE IN TAX GENERATION:
Original Assessed Value of the Redevelopment Project:
$28,010.00
Assessed Valuation Added to the Redevelopment Project:
$5,039,080.00
Anticipated Assessed Value at Time of District Termination:
$19,528,588.00
Total Amount of Base Year EATs:
$0.00
Total Amount of Base Year PILOTs:
$1,310.00
Total Annual EATs Anticipated at Time of District Termination:
$0.00
Total Annual PILOTs Anticipated at Time of District Termination:
$0.00
Percentage of EATs Captured:
0%
Total Years Anticipated to Capture EATs:
0
Percentage of PILOTs Captured:
5%
Total Years Anticipated to Capture PILOTs:
23