Name of City and/or County:
West Plains
Name of Plan or Project:
S. U.S. Hwy 160 Corridor/Porter Wagoner Bl. R.P.
Report Period:
4/1/2008 to 3/31/2009
Name of the Person Who Prepared this Annual Report:
Dixie Williams, Finance Director
City or County Contact Agency:
Royce Fugate, P.E., City Administrator
Private Sector Developer:
Wal-Mart and various other developers
Person:
Ted Frumpkin, et. al.
Original Date Plan/Project Approved:
5/19/1994
Most Recent Plan Amendment:
5/22/2003
School District:
West Plains R-7 Schools
A large area along the U.S. Hwy 63 bypass from downtown south to the Hwy 63 and Hwy 160 junction in West Plains.
Description of Plan/Project:
Construction of multiple development projects in eight phases including a Wal-Mart store, shopping malls, downtown square, street and infrastructure improvements throughout the area, soil erosion mediation works, parcel assembly for MSU.
Plan/Project Status:
Fully Operational
Area Type:
Blight, Conservation & Economic Development
How was the "but-for" Determination Made?:
Unusual/extraordinary costs made the project financially unfeasible in the market, required significant public infrastructure to remedy existing inadequate conditions and capacity to support development.
Number of Relocated Residences During This Report Period:
0
Number of Relocated Businesses During This Report Period:
0
Number of Parcels Acquired Through Use of Eminent Domain Power During This Report Period:
0
Identify Any Businesses That Have Relocation to the Redevelopment Area During this Report Period:
Estimate of New Jobs:
201
Estimate of Retained Jobs:
30
TIF REVENUE DEPOSITS TO THE SPECIAL ALLOCATION FUND AS OF THE REPORT DATE:
Payments in Lieu of Taxes (PILOTs):
Total Received since inception:
$0.00
Amount on Hand: (As of Report Date)
$0.00
Economic Activity Taxes (EATs):
Total Received since inception:
$2,633,462.79
Amount on Hand: (As of Report Date)
$250,967.63
Total Revenue on hand in the Special Allocation Fund as of Report Date:
EXPENDITURES FOR TOTAL PROJECT COSTS FUNDED BY TIF:
Total Since Inception:
Report Period Only:
Public Infrastructure (streets, utilities, etc):
Site Development (grading, dirt moving, etc):
Rehab of Existing Buildings:
Acquisition of Land or Buildings:
AMOUNT PAID ON DEBT SERVICES:
Payments of principal and interest on outstanding bonded debt:
Since Inception:
$2,481,270.60
This Reporting Period:
$0.00
Reimbursement of developer for eligible cost:
This Reporting Period:
$0.00
Reimbursement to city/county (or other public entity) for eligible costs:
This Reporting Period:
$0.00
ANTICIPATED TIF REIMBURSEMENT COSTS:
Public Infrasture and Site Development Costs:
$1,960,385.00
Property Acquisition and Relocation Costs:
$0.00
Project Implementation Costs:
$0.00
Total Anticipated TIF Reimbursable Project Costs:
$3,904,249.00
ANTICIPATED TOTAL PROJECT COSTS:
TIF FINANCING METHOD:
Pay-as-you-go; Loan; Other Bond
MATURITY OF TIF OBLIGATIONS:
Original Estimate (# of Years to Retirement):
23
Current Anticipated Estimate (# of Year to Retirement):
8
ESTIMATED INCREASE IN TAX GENERATION:
Original Assessed Value of the Redevelopment Project:
$0.00
Assessed Valuation Added to the Redevelopment Project:
$0.00
Anticipated Assessed Value at Time of District Termination:
$0.00
Total Amount of Base Year EATs:
$0.00
Total Amount of Base Year PILOTs:
$0.00
Total Annual EATs Anticipated at Time of District Termination:
$0.00
Total Annual PILOTs Anticipated at Time of District Termination:
$0.00
Percentage of EATs Captured:
50%
Total Years Anticipated to Capture EATs:
23
Percentage of PILOTs Captured:
0%
Total Years Anticipated to Capture PILOTs:
0