Flood Protection Plan Redevelopment

Section 1: Description of the Plan and Project
Hannibal
Flood Protection Plan Redevelopment
7/1/2008 to 6/30/2009
Douglas Warren
Douglas Warren, City of Hannibal
573-221-0111
US Army Corps of Engineers (no private developer)
Barack Obama, POTUS
1/2/1988
3644
6
18
Hannibal School District
The project is a floodwall built on the west bank of the Mississippi River in downtown Hannibal, The Project Area includes all of the Downtown Historic and Business District east of 3rd St, south of the old Hwy 36 bridge and north of Lyon Street.
Construction of a new floodwall levy, installation of pumps for stormwater remediation, gates for river access during normal water level conditions, earthenwork wall, removal of old grain silos and vacant warehouses
Fully Operational
Blight, Conservation & Economic Development
Unusual/extraordinary costs made project financially unfeasible in the market, required significant public infrastructure investment to remedy existing inadequate conditions and capacity to support development.
0
0
0
Name Address Phone Number New or Relocated? Rel. from What City/County
Dannie Nicoles 119 N. Main Street (573) 221-5066 New
Hole in the Wall Hobbies 207 N. Main Street (573) 221-3434 New
Main Street Theater/B & B Theater Group 100 S. Main Street (573) 248-1966 New
Main Street Wine Stoppe 303 N. Main Street (573) 231-1007 New
Pampered Pawz 116 N. Third Street (573) 221-2007 New
0
0
0
0
Section 2: Tax Increment Financing Revenues
$782,428.29
$302,196.00
$0.00
$0.00
$302,196.00
$664,285.56
$0.00
$0.00
$0.00
$560,000.00
$0.00
$0.00
$0.00
$0.00
$18,900.00
$510,000.00
$528,900.00
$1,753,185.56
TIF Bond, Loan, Other (USACE investment)
23
2
$1,324,550.00
$2,231,980.00
$3,629,453.23
$0.00
$4,967.00
$0.00
$151,300.00
%
88%
23