Success Notification Overlay
Failure Notification Overlay

Redevelopment Plan for the Ozora Area TIF

Section 1: Description of the Plan and Project
Ste. Genevieve
Redevelopment Plan for the Ozora Area TIF
10/1/2018 to 9/1/2019
Leslie Seabaugh, SEMO Regional Planning Commission
573-883-3000
Crawford Oil
Randy Crawford
573-359-1213
09312
116
3
Ste. Genevieve R-2
114 acres in the northwest quadrants of I-55 and State Route N
Rehabilitate Ozora truck stop and country store and environmental remediation.
Under Construction
0
0
0

- None -

70
70
0
0
Section 2: Tax Increment Financing Revenues
$46,198.33
$1,039.54
$81,842.46
$0.00
$1,039.54
$133,963.32
$22,202.73
$0.00
$0.00
$0.00
$0.00
$4,850,000.00
$100,000.00
$580,000.00
$400,000.00
$0.00
$5,930,000.00
$14,500,000.00
23
16
$586,260.00
$197,660.00
$6,128,128.00
$800.00
$25,937.00
$214,012.00
$0.00
50%
23
100%
23