Name of City and/or County:
Higginsville
Name of Plan or Project:
First Amended I-70 Interchange Plan Project 1
Report Period:
9/30/2006 to 9/30/2007
Name of the Person Who Prepared this Annual Report:
Richard Reyna, City Clerk, Asst. Administrator
City or County Contact Agency:
Richard Reyna, City Clerk, Asst. Administrator
Private Sector Developer:
Pilot Travel Centers, LLC / Williams Travel Center
Person:
Property Tax Department
Original Date Plan/Project Approved:
6/7/1999
Ordinance Number:
1831-1832
Most Recent Plan Amendment:
12/30/1999
School District:
Lafayette County C-1
67.5 acres located in the northwest quadrant of the I-70/MO-13 interchange
Description of Plan/Project:
Extension of necessary utilities, demolition and other site prep for construction of a Pilot Travel Center facility
Plan/Project Status:
Fully operational
How was the "but-for" Determination Made?:
Unusual/extraordinary costs made project financially unfeasible in the market, required significant public infrastructure investment to remedy existing inadequate conditions and capacity to support development
Number of Relocated Residences During This Report Period:
0
Number of Relocated Businesses During This Report Period:
0
Number of Parcels Acquired Through Use of Eminent Domain Power During This Report Period:
0
Identify Any Businesses That Have Relocation to the Redevelopment Area During this Report Period:
Estimate of New Jobs:
100
Estimate of Retained Jobs:
TIF REVENUE DEPOSITS TO THE SPECIAL ALLOCATION FUND AS OF THE REPORT DATE:
Payments in Lieu of Taxes (PILOTs):
Total Received since inception:
$405,249.55
Amount on Hand: (As of Report Date)
$0.00
Economic Activity Taxes (EATs):
Total Received since inception:
$281,230.31
Amount on Hand: (As of Report Date)
$0.00
Total Revenue on hand in the Special Allocation Fund as of Report Date:
EXPENDITURES FOR TOTAL PROJECT COSTS FUNDED BY TIF:
Total Since Inception:
Report Period Only:
Public Infrastructure (streets, utilities, etc):
Site Development (grading, dirt moving, etc):
Rehab of Existing Buildings:
Acquisition of Land or Buildings:
AMOUNT PAID ON DEBT SERVICES:
Payments of principal and interest on outstanding bonded debt:
Since Inception:
$683,843.86
This Reporting Period:
$118,030.66
Reimbursement of developer for eligible cost:
This Reporting Period:
$0.00
Reimbursement to city/county (or other public entity) for eligible costs:
Since Inception:
$2,578.67
This Reporting Period:
$740.00
ANTICIPATED TIF REIMBURSEMENT COSTS:
Public Infrasture and Site Development Costs:
$707,100.00
Property Acquisition and Relocation Costs:
$0.00
Project Implementation Costs:
$116,500.00
Total Anticipated TIF Reimbursable Project Costs:
$1,626,880.00
ANTICIPATED TOTAL PROJECT COSTS:
$8,100,000.00
TIF FINANCING METHOD:
Loan
MATURITY OF TIF OBLIGATIONS:
Original Estimate (# of Years to Retirement):
23
Current Anticipated Estimate (# of Year to Retirement):
17
ESTIMATED INCREASE IN TAX GENERATION:
Original Assessed Value of the Redevelopment Project:
$15,438.00
Assessed Valuation Added to the Redevelopment Project:
$965,597.00
Anticipated Assessed Value at Time of District Termination:
$3,461,250.00
Total Amount of Base Year EATs:
$0.00
Total Amount of Base Year PILOTs:
$0.00
Total Annual EATs Anticipated at Time of District Termination:
$6,418,465.00
Total Annual PILOTs Anticipated at Time of District Termination:
$6,418,465.00
Percentage of EATs Captured:
50%
Total Years Anticipated to Capture EATs:
23
Percentage of PILOTs Captured:
100%
Total Years Anticipated to Capture PILOTs:
23