approximately 54 acres on and around the courthouse square in downtown perryville
The City will fund grants to various property owners for rehabilitation and stabilization of commercial buildings, faade improvements, signage, electrical, water and sewer improvements.
Under Construction
Conservation
Project had unusual/extraordinary costs that made the project financially unfeasible in the market place. Project required significant public infrastructure investment to remedy existing inadequate conditions. Project required significant public infrastructure investment to construct adequate capacity to support the project.
0
0
0
- None -
100
80
50
0
Section 2: Tax Increment Financing Revenues
$0.00
$0.00
$73,447.42
$8,890.16
$8,890.16
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$5,250,000.00
$500,000.00
$1,787,500.00
$1,153,750.00
$0.00
$12,691,750.00
$33,000,000.00
Pay-as-you-go; General Obligation Bonds; Industrial Revenue Bond; TIF Notes