Success Notification Overlay
Failure Notification Overlay

Redevelopment Plan for the Highway 51/61 Tax

Section 1: Description of the Plan and Project
Perry County
Redevelopment Plan for the Highway 51/61 Tax
10/1/2013 to 9/1/2014
Chauncy Buchheit
Perry County Commission
5735474242
none
1/1/2010
145-116
27
Perry County 32
The Redevelopment Area lies mainly north of U. S. Highway 61 and along both sides of State Highway 51 in the general vicinity of the U. S. Highway 61 and State Highway 51 intersection.The Redevelopment Area consists of 1 approximately 699 acres .
Project 1 includes street, water lines, sewer lines, and gas main extensions to serve the Gilster-Mary Lee site, as well as property acquisition for the site. In addition, parking lot pavement is being proposed for the Gilster-Mary Lee site in order to cut down the dust associated with heavy truck traffic in and out of the Industrial Park.
Under Construction
Blight
Project had unusual/extraordinary costs that made the project financially unfeasible in the market place. Project required significant public infrastructure investment to remedy existing inadequate conditions. Project required significant public infrastructure investment to construct adequate capacity to support the project. Project required parcel assembly and/or relocation costs.
0
0
0

- None -

500
451
200
200
Section 2: Tax Increment Financing Revenues
$157,094.00
$157,094.00
$0.00
$0.00
$157,094.00
$0.00
$0.00
$0.00
$0.00
$148,120.04
$47,057.50
$5,132,500.00
$530,000.00
$1,742,500.00
$1,072,250.00
$0.00
$12,427,250.00
$46,800,000.00
Pay-as-you-go; General Obligation Bonds; Industrial Revenue Bond; TIF Notes
23
23
$482,946.00
$1,090,625.00
$15,826,407.00
$0.00
$23,622.91
$12,686.00
$0.00
50%
23
100%
23