Name of City and/or County:
Appleton City
Name of Plan or Project:
1st Amended & Restated Appleton City Downtown TIF
Report Period:
2012-10-01 to 2013-09-30
Name of the Person Who Prepared this Annual Report:
Judy Wood
City or County Contact Agency:
Judy Wood, City Clerk
Private Sector Developer:
Food Fair of Appleton City, LLC & Farmhouse Kit.
Person:
William Wetter & Eric Christie & Terry Powell & Li
Phone:
660-476-2131;660-476-2300
Original Date Plan/Project Approved:
2003-12-01
Most Recent Plan Amendment:
11/15/2012
School District:
Appleton City R-2 School District
Redevelopment Area is located in downtown Appleton City comprising about 17 city blocks west of Hickory St, east of the railroad tracks, south of 6th Street and along and on both sides of 4th street.
Description of Plan/Project:
The city has approved Phase IV of the TIF Plan. The intent of the Original Plan was to demolish as exisiting motel north of 4th Street to construct a Dollar General Store.
Plan/Project Status:
Fully operational
How was the "but-for" Determination Made?:
Number of Relocated Residences During This Report Period:
0
Number of Relocated Businesses During This Report Period:
0
Number of Parcels Acquired Through Use of Eminent Domain Power During This Report Period:
0
Identify Any Businesses That Have Relocation to the Redevelopment Area During this Report Period:
Estimate of Retained Jobs:
25
TIF REVENUE DEPOSITS TO THE SPECIAL ALLOCATION FUND AS OF THE REPORT DATE:
Payments in Lieu of Taxes (PILOTs):
Total Received since inception:
$134,166.72
Amount on Hand: (As of Report Date)
$4,341.94
Economic Activity Taxes (EATs):
Total Received since inception:
$244,723.60
Amount on Hand: (As of Report Date)
$3,552.50
Total Revenue on hand in the Special Allocation Fund as of Report Date:
EXPENDITURES FOR TOTAL PROJECT COSTS FUNDED BY TIF:
Total Since Inception:
Report Period Only:
Public Infrastructure (streets, utilities, etc):
Site Development (grading, dirt moving, etc):
Rehab of Existing Buildings:
Acquisition of Land or Buildings:
$3,761,610.00
$125,000.00
AMOUNT PAID ON DEBT SERVICES:
Payments of principal and interest on outstanding bonded debt:
This Reporting Period:
$0.00
Reimbursement of developer for eligible cost:
This Reporting Period:
$0.00
Reimbursement to city/county (or other public entity) for eligible costs:
This Reporting Period:
$0.00
ANTICIPATED TIF REIMBURSEMENT COSTS:
Public Infrasture and Site Development Costs:
$0.00
Property Acquisition and Relocation Costs:
$0.00
Project Implementation Costs:
$0.00
Total Anticipated TIF Reimbursable Project Costs:
$0.00
ANTICIPATED TOTAL PROJECT COSTS:
$2,270,093.00
TIF FINANCING METHOD:
Pay-as-you-go
MATURITY OF TIF OBLIGATIONS:
Original Estimate (# of Years to Retirement):
Current Anticipated Estimate (# of Year to Retirement):
ESTIMATED INCREASE IN TAX GENERATION:
Original Assessed Value of the Redevelopment Project:
$814,700.00
Assessed Valuation Added to the Redevelopment Project:
$262,100.00
Anticipated Assessed Value at Time of District Termination:
$1,075,452.00
Total Amount of Base Year EATs:
$159,102.00
Total Amount of Base Year PILOTs:
$52,054.00
Total Annual EATs Anticipated at Time of District Termination:
$810,821.81
Total Annual PILOTs Anticipated at Time of District Termination:
$1,573,870.29
Percentage of EATs Captured:
50%
Total Years Anticipated to Capture EATs:
23
Percentage of PILOTs Captured:
100%
Total Years Anticipated to Capture PILOTs:
23