Name of City and/or County:
Arnold
Name of Plan or Project:
Arnold Triangle Redevelopment Plan
Report Period:
2011-09-01 to 2012-08-31
Name of the Person Who Prepared this Annual Report:
Deborah Lewis, Finance Director
City or County Contact Agency:
Robert T. Shockey, Interim City Administrator
Private Sector Developer:
THF Arnold Triangle Development, LLC
Original Date Plan/Project Approved:
2005-09-15
Most Recent Plan Amendment:
School District:
Fox C-6 School District
50ac located at the southwest corner of I-55 and MO-141 in Arnold
Description of Plan/Project:
Development of the existing commerical and residential properties for retail and commerical purposes.
Plan/Project Status:
Fully Operational
How was the "but-for" Determination Made?:
Unusual/extraordinary costs made the project financially unfeasible in the market, required significant public infrastructure investment to remedy exisiting inadequate conditions and required parcel ass'y and/or relocation costs.
Number of Relocated Residences During This Report Period:
0
Number of Relocated Businesses During This Report Period:
0
Number of Parcels Acquired Through Use of Eminent Domain Power During This Report Period:
0
Identify Any Businesses That Have Relocation to the Redevelopment Area During this Report Period:
Estimate of New Jobs:
300
Estimate of Retained Jobs:
5
TIF REVENUE DEPOSITS TO THE SPECIAL ALLOCATION FUND AS OF THE REPORT DATE:
Payments in Lieu of Taxes (PILOTs):
Total Received since inception:
$2,652,017.53
Amount on Hand: (As of Report Date)
$0.00
Economic Activity Taxes (EATs):
Total Received since inception:
$6,701,697.05
Amount on Hand: (As of Report Date)
$34,542.18
Total Revenue on hand in the Special Allocation Fund as of Report Date:
EXPENDITURES FOR TOTAL PROJECT COSTS FUNDED BY TIF:
Total Since Inception:
Report Period Only:
Public Infrastructure (streets, utilities, etc):
Site Development (grading, dirt moving, etc):
Rehab of Existing Buildings:
Acquisition of Land or Buildings:
AMOUNT PAID ON DEBT SERVICES:
Payments of principal and interest on outstanding bonded debt:
Since Inception:
$6,906,311.19
This Reporting Period:
$2,175,568.75
Reimbursement of developer for eligible cost:
This Reporting Period:
$0.00
Reimbursement to city/county (or other public entity) for eligible costs:
This Reporting Period:
$0.00
ANTICIPATED TIF REIMBURSEMENT COSTS:
Public Infrasture and Site Development Costs:
$0.00
Property Acquisition and Relocation Costs:
$10,000,000.00
Project Implementation Costs:
$11,000,000.00
Total Anticipated TIF Reimbursable Project Costs:
$21,000,000.00
ANTICIPATED TOTAL PROJECT COSTS:
$90,000,000.00
TIF FINANCING METHOD:
TIF Bond
MATURITY OF TIF OBLIGATIONS:
Original Estimate (# of Years to Retirement):
23
Current Anticipated Estimate (# of Year to Retirement):
23
ESTIMATED INCREASE IN TAX GENERATION:
Original Assessed Value of the Redevelopment Project:
$1,700,400.00
Assessed Valuation Added to the Redevelopment Project:
$12,436,800.00
Anticipated Assessed Value at Time of District Termination:
$12,712,094.00
Total Amount of Base Year EATs:
$25,002.32
Total Amount of Base Year PILOTs:
$128,213.00
Total Annual EATs Anticipated at Time of District Termination:
$3,494,086.00
Total Annual PILOTs Anticipated at Time of District Termination:
$878,007.00
Percentage of EATs Captured:
50%
Total Years Anticipated to Capture EATs:
23
Percentage of PILOTs Captured:
100%
Total Years Anticipated to Capture PILOTs:
23