Success Notification Overlay
Failure Notification Overlay

60/61 TIF District

Section 1: Description of the Plan and Project
Sikeston
60/61 TIF District
7/1/2009 to 6/30/2010
Carroll L. Couch
Carroll L. Couch, City Clerk
573-471-2511
Four Corners Development Co, Inc.
R. Scott Matthews
573-471-1960
6/5/2000
5328, 5329, 5333
6/3/2002
5461
160
27
Sikeston R-VI
The project area is located at the intersection of US Highway 60 and US Highway 61 in Sikeston.
Development of a combination of commercial and residential structures.
Fully operational
Blight, Economic Development
The project required significant public infrastructure investment to remedy existing inadequate conditions and capacity to support development.
0
0
0

- None -

180
387
80
100
Section 2: Tax Increment Financing Revenues
$933,858.00
$2,770.00
$3,007,230.00
$22,008.00
$24,778.00
$4,133,424.00
$804,360.00
$0.00
$0.00
$0.00
$0.00
$6,775,000.00
$75,000.00
$150,000.00
$0.00
$0.00
$7,000,000.00
$43,707,000.00
TIF Bond; TIF Notes
15
15
$2,592,760.00
$3,488,880.00
$6,000,000.00
$56,031.00
$1,830,660.00
$8,045,776.00
$5,640,619.00
50%
11
100%
11